The Navy financed 326 days at sea by borrowing against future dry dock capacity. The bill is now due, and the industrial base cannot make the payment.

By Ryan Murray· Director of Marketing & Development
1 min read
READINESS MORTGAGE: The Current Conversation cover

The Readiness Mortgage

MD Marine Electric | The Current Conversation

Three hundred thirty nine days. That is how long the destroyer Spruance stayed underway before breaking a record for longest destroyer deployment that had stood since World War II.¹ The aircraft carrier Gerald R. Ford beat its own record earlier this year, completing a 326 day deployment in May, eclipsing the 294 day mark set by the Abraham Lincoln in 2019 and 2020.¹ The destroyer McFaul came home to Norfolk on Oct. 23 after 332 days at sea, having spent eleven months integrated with three different carrier strike groups providing anti air warfare and surface fire support.¹

Those numbers read like achievements. The Navy's own leadership is telling Congress and the trade press they are closer to liabilities.

Vice Chief of Naval Operations Adm. James Kilby said as much at an Oct. 8 hearing of the National Commission on the Future of the Navy. Operations in the Middle East, he said, have produced <cite index="5-3">"artificially high combat surge ready rates" because ships remain at sea on extended deployments and have yet to return from the region

Share this article
Email
The Concurrency Cascade
Naval Procurement

The Concurrency Cascade

The CBO analyzed 314 maintenance events over 14 years and found the same pattern repeating. Maintenance takes 20 to 100 percent longer than scheduled. This is not a contractor performance problem. It is a structural one.

March 20269 min read
The Bonding Gap
Naval Procurement

The Bonding Gap

The Miller Act has protected federal construction subcontractors for 91 years. Federal vessel repair contracts are classified as service contracts. And the protection does not apply. Mare Island Dry Dock exposed what that means in practice.

February 202611 min read
Naval Procurement

The Modernization Seam

The Navy treats ship repair and system modernization as two separate activities. They are not. They are the same activity executed by different contractors under different contracts in the same hull at the same time. The space between them is where most vessel projects fail.

January 20268 min read